James G. Staat Tuckpointing & Waterproofing is 90% complete. Hyde Sheet Metal is doing the copper material and they are nearing the top. The new lightning protection work began this week. And we are staying within budget! Our owner's rep, Bill Ahal, climbed to the top this week to check the work and took pictures while her was there! The General Contractor, ISC Contracting, has ordered the new louvers and preparing for the interior work on the bell tower soon. Brand/Safway will return when it's all complete to remove the scaffolding. And the cross is being cleaned and restored too!